The order metal siding goes on

Metal siding goes on in order: a taped weather barrier with flashed penetrations, furring for a vented rainscreen gap, a level base flashing and plumb first panel, then screws driven centered in the slot only to the washer’s kiss so the metal can expand and contract without oil-canning.

Source: Install order per IRC R703 + metal-panel manufacturer specs

What this diagram shows

A four-panel walkthrough of metal siding install order. Panel 1: a weather-resistive barrier over sheathing with taped seams and a flashed pipe penetration. Panel 2: furring strips hold a vented rainscreen gap of at least three-eighths inch between the wall and the panel plane. Panel 3: a level base Z-flashing is set and the first panel is plumbed to a chalk line. Panel 4: a screw is driven centered in the panel’s slotted hole and only to the point the washer kisses the flange, leaving room for thermal movement, before the next panel interlocks.

Use this diagram — free

You're welcome to use this diagram on your own site, blog, handout, or lesson at no cost. The only condition is a visible credit link back to the source page. Copy the snippet below and paste it into your page — the credit is already included.

Please keep the credit link intact and don't alter the diagram itself. Redistribution as part of a competing diagram library or template pack isn't permitted. Questions? Reach us via the site.

Metal Siding Guide

This diagram appears in our in-depth guide.

Read the guide

Related diagrams